225 kV Ghana - Burkina Faso - Mali Interconnection Project

Transmission
Objective
To interconnect the networks of Ghana, Burkina Faso and Mali for export of lower cost power from Ghana
Project Status
Pre-investment Studies completed and Environmental Permits issued in each of three countries. Institutional Study also completed
useful information
Type of StudyFeasibility + ESIA + Bidding Docs
Cost of Study (US$ millions)2 700
Funds Secured (US$ millions)2 700
Funding SourcesEIB, USAID