Ligne de Transport 161 kV Tumu-Han-Wa (Ghana)

Transmission
Objective
To close northern transmission loop in Ghana as pre-condition for Ghana - Burkina Faso - Mali interconnection
Project Status
The construction of the 161 kV Tumu Substation and 161 kV Tumu-Han-Wa transmission line was energized on February 3, 2015. Installation of SCADA/Communication equipment at the 161 lkV Sawla, Wa and Tumu Substations was completed and the facilities were commissioned
Follow up Actions Required
WAPP and GRIDCo to monitor the performance of the line
useful information
In service year2015
Project Cost (US$ millions)71
Funds Secured (US$ millions)71
Funding SourcesSociete General Bank of France