28th WAPP Donor Coordination Meeting
10.11.2016
28th WAPP Donor Coordination Meeting
”STATUS OF DELIVERY OF WAPP PRIORITY PROJECTS”
The WAPP Interconnected System today has 9 ECOWAS Member States electrically linked with reinforced interconnections.
These have been made possible due to:
330 kV West (Nigeria) – Sakete (Benin) Interconnection Project – 70 km
- Construction completed and project operational since 2007
- Was funded by AfDB, BOAD, EBID as well as Gov’ts of Nigeria and Togo/Benin
- WAPP ICC monitoring of line indicates that Interconnection could be saturated by 2018/2019
225 kV Bobo – Ouaga Tranmission Line Project IN BURKINA – 339 km:
- Construction completed and project operational since 2009
- Fully funded by WB, AFD, EIB, Danida, Danish Mixed Credit and Gov’t of Burkina
330 kV Aboadze - Volta Transmission Line Project IN GHANA – 219 km:
- Construction completed and project operational since 2010
- Fully funded by WB , EIB, Kuwaiti Fund and Government of Ghana
225 kV Cote d’Ivoire - Mali Interconnection Project – 234 km:
- Construction completed and project operational since 2012
- Funded by EBID , BOAD and Governments of India, Mali and Cote d’Ivoire
- Sikasso – Bamako segment being implemented by Government of Mali
60 MW Felou Hydropower Project UNDER OMVS:
- Construction completed and project operational since 2013
- Funded fully by WB and EIB together with Gov’ts of Senegal, Mali and Mauritania
240 MW Kaleta Hydropower Project in Guinea:
- Construction completed and project operational since 2015
- Implemented by the Gov’t of Guinea with support from China Exim Bank
COMPLETE INTEGRATION OF POWER SYSTEMS OF MAINLAND ECOWAS MEMBER STATES
The 2016 – 2019 WAPP Business Plan has as primary goal among others to further reinforce the WAPP Interconnected System and achieve a complete integration of the 14 mainland ECOWAS Member States by 2019.