Objective
To augment hydro power capacity of the OMVG power system
Project Status
The construction of the 240 MW Kaleta hydropower project was completed and inaugurated on September 28, 2015
Follow up Actions Required
WAPP ICC to monitor performance
useful information
In service year2015
Cost of Study (US$ millions)458
Funds Secured (US$ millions)458
Funding SourcesGov't of Guinea, Eximbank China