225 kV Guinea - Mali Interconnection Project
Installation date:
01.27.2016
Others
Objective
To interconnect the networks of
Guinea and Mali
Project Status
The first Donors' Round-table organized from
January 27th to 28th, 2016 has agreed to integrate the line Linsan -
Fomi in the project.The estimated cost of the project is €418.76 million
including an approximation for Linsan - Fomi of about €151,43 million.
The Donors have agreed to proceed with the main interconnection
whilst the pre-investment studies on Linsan - Fomi are being
concluded
Follow up Actions Required
WAPP to mobilize
financing for project
implementation
useful information
In service year | 2020 |
Project Cost (US$ millions) | 565 |
Financing Under Negotiation (US$ millions) | 379 |
Financing Gap (US$ millions) | 186 |
Funding Sources | AfDB, EIB, BOAD, KfW, EBID, AFD, IsDB and WB |