225 kV Guinea - Mali Interconnection Project

Installation date: 
01.27.2016
Others
Objective
To interconnect the networks of Guinea and Mali
Project Status
The first Donors' Round-table organized from January 27th to 28th, 2016 has agreed to integrate the line Linsan - Fomi in the project.The estimated cost of the project is €418.76 million including an approximation for Linsan - Fomi of about €151,43 million. The Donors have agreed to proceed with the main interconnection whilst the pre-investment studies on Linsan - Fomi are being concluded
Follow up Actions Required
WAPP to mobilize financing for project implementation
useful information
In service year2020
Project Cost (US$ millions)565
Financing Under Negotiation (US$ millions)379
Financing Gap (US$ millions)186
Funding Sources AfDB, EIB, BOAD, KfW, EBID, AFD, IsDB and WB