450 MW WAPP Maria Gleta Regional Power Generation Facility in Benin
Installation date:
04.14.2015
Generation
Objective
To augment the power generation
capacity of the sub-region
Project Status
In the framework of the Update of
Feasibility Studies for the power plants, Africa Finance Corporation
(AFC) has recruited a consultant who transmitted the Final
Prefeasibility Report adopted from December 14th to 15th, 2015 by the
JIC of the project.
On April 11th, 2016 the Directors General and Chief Executives of the
utilities involved in the project, satisfied on the results of the
prefeasibility study, asked AFC to move to the detailed feasibility
study.
The comments of stakeholders on the ToR and the methodology of the
detailed feasibility study submitted by the Consultant, were sent to
AFC on August 18th, 2016 for consideration.
The Provisional Feasibility Study Report is expected in early
December, 2016
Follow up Actions Required
WAPP to implement
project with AFC
useful informations
In service year | 2020 |
Project Cost (US$ millions) | 652 |
Financing Under Negotiation (US$ millions) | 652 |
Funding Sources | AFC, Utilities |