Rehabilitation of Nangbeto Hydropower plant in Togo/Benin
Generation
Objective
To improve delivery of ancillary
services and sub-regional system
balancing capabilities
Project Status
The Project funding Agreements between KfW, the
Governments of Benin, Togo and the CEB have been signed. The
recruitment of the Owner's Engineer has been completed and the
preparation of the bidding documents in progress
Follow up Actions Required
WAPP Secretariat to
follow up with CEB on
project implementation
useful information
In service year | 2018 |
Project Cost (US$ thousands) | 24 |
Funds Secured (US$ thousands) | 24 |
Funding Sources | KfW, CEB |